ACTION A05.- Restoration, upgrading and improvement of the Luanco – Cabo Peñas coastal path
Programme axis
2. Energy Efficiency Improvement
The coastal path is a route for walking and cycling that offers wide sea views over well-preserved landscapes, with cliffs, beaches, dune systems and a rich variety of wildlife and plants. Some of its birdwatching spots are well known among birdwatchers.
The aim of the action is to turn the coastal path into a route that can be cycled as well as walked, catering for both walkers and cyclists, and to make the most of its landscape and natural value to attract national and international visitors. At present some sections can already be cycled, others require cyclists to carry their bikes in places, and others are much harder to ride because of the terrain. For those, there are alternative routes running alongside or close to the path, but they have not been upgraded or signposted.
Years of use had left the coastal path in poor condition, so the necessary works have been carried out to restore, stabilise and enhance the existing coastal path.
The works have focused on keeping users safe, making the infrastructure more resilient to water erosion and the marine environment, and enhancing the sustainable tourism experience through better accessibility, new furniture and the official approval of the route.
The work has been tailored to the actual terrain and its needs, with both continuous and spot interventions along the existing route. On paths and surfaces, vegetation was cleared and landslide debris removed to restore the usable width, and damaged sections were regraded, compacted and topped up with new material. New footpaths separated from road traffic have also been opened along the GO-1 road, the road surface on the Bañugues access road has been renewed, and the Moniello car park has been partly returned to nature to stop vehicles driving and parking haphazardly.
To stabilise the ground and manage drainage, ditches have been cleaned and reshaped and new cross drains have been built to prevent water erosion and channel rainwater. These measures were complemented by stone sub-bases in areas prone to waterlogging and by rock-armour walls on the GO-1 and at the La Cueva stream to keep the path and its slopes stable.
Lastly, on facilities and signage, all the timber structures have been fully overhauled: they were cleaned, pressure-washed and treated with wood stain, and railings, stairs and steps were replaced where there was a risk of falls. New footbridges have been installed over watercourses, along with rustic benches in rest areas. Finally, directional and interpretive signs have been put up in line with the criteria of the FEDME (Spanish Mountain Sports and Climbing Federation) and the “Senderos de Asturias” manual, so that the route can be officially approved by the FEMPA (Asturias Mountain Sports Federation). Road signs have also been installed in Moniello to manage traffic.
A05.1.- Project design, site supervision and health and safety coordination for the “Restoration, upgrading and improvement of the Luanco – Cabo Peñas coastal path”
• Procurement file: CON/2024/62
• Public tender on the Spanish Public Sector Procurement Platform: https://contrataciondelestado.es/wps/poc?uri=deeplink:detalle_licitacion&idEvl=UpNTQV3N7jFJ8Trn0ZPzLw%3D%3D
• Awarded to: TALAVERA QUINTERO INGENIEROS S.R.L.
• Contract award amount: €22,869.00
• Execution period: 50 days (project delivery)
• Work status: completed
A05.2.- Works for the “Restoration, upgrading and improvement of the Luanco – Cabo Peñas coastal path”
• Procurement file: CON/2024/84
• Public tender on the Spanish Public Sector Procurement Platform: https://contrataciondelestado.es/wps/poc?uri=deeplink:detalle_licitacion&idEvl=EFB0rzELOL2sNfRW6APEDw%3D%3D
• Awarded to: DESARROLLOS Y METAS S.L.
• Execution amount: €327,157.91
• Execution period: 6 months
• Work status: completed